docs(phase-01): complete phase execution
This commit is contained in:
@@ -4,7 +4,7 @@ milestone: v1.0
|
||||
milestone_name: milestone
|
||||
status: verifying
|
||||
stopped_at: Phase 1 complete — all 5 FW requirements approved on hardware
|
||||
last_updated: "2026-04-03T11:36:20.546Z"
|
||||
last_updated: "2026-04-03T11:41:55.158Z"
|
||||
last_activity: 2026-04-03
|
||||
progress:
|
||||
total_phases: 4
|
||||
@@ -25,8 +25,8 @@ See: .planning/PROJECT.md (updated 2026-04-03)
|
||||
|
||||
## Current Position
|
||||
|
||||
Phase: 01 (esp32-firmware) — EXECUTING
|
||||
Plan: 4 of 4
|
||||
Phase: 2
|
||||
Plan: Not started
|
||||
Status: Phase complete — ready for verification
|
||||
Last activity: 2026-04-03
|
||||
|
||||
|
||||
Reference in New Issue
Block a user